96 critical questions before an industrial data-center decision
24 areas to resolve, from the first land-use application through operation and closure. Apply this checklist separately to each project. A proposal, projected benefit or directory listing does not establish an approval or operating outcome.
Every answer needs a record, an accountable agency and an actual deadline. Track Unknown, Reported, Verified, Contradicted, or Not applicable with written rationale. For each answer record: project and parcel; answer or explicit unknown; source URL/document/page; evidence status; author/firm and payer; reviewer and review date; responsible agency; applicable condition/permit; milestone and deadline; request ID; date requested/received; remaining gap and next action. A marketing claim is not a verified outcome. Not every study is legally required for every site: document the agency's applicability decision, waiver and rationale rather than assuming a universal requirement. Dates must come from the applicable local procedure or actual receipt/notice; do not invent statutory deadlines.
DCAP questions tracker Fort Lupton evidence
IC-01 · Identity, ownership and land
- Who are the applicant, developer, landowner, operator, tenants, parent companies, financing entities and authorized representatives?
- What parcels, legal descriptions, acreage, deed instruments, options, easements, water and mineral interests define the site?
- What earlier names or related applications identify the same project?
- Which identity claims are documented and which remain unknown?
IC-02 · Jurisdiction and zoning
- Which government controls each parcel and each utility, road, drainage and fire service?
- What are the current zoning, comprehensive-plan designation and allowed uses; is a data center separately defined?
- Which annexation, rezoning, PUD, special-use, subdivision, variance or development agreements are needed?
- What setbacks, height, lot coverage, screening, residential and school buffers apply?
IC-03 · Approval scope and conditions
- What precisely is being approved: land use, campus, first phase, utility facilities or building permits?
- What are maximum full-buildout acreage, buildings, floor area, height, electrical load and cooling demand?
- Which conditions are binding, which are promises, and who can change them?
- Which agency approvals remain outstanding and what prohibits operation until obtained?
IC-04 · Timeline, votes and public notice
- What are the dated pre-application, filing, completeness, referral, hearing, vote and permit milestones?
- What notices, recipients, maps, posting affidavits and consultation records establish public notice?
- Who moved, seconded and voted on each action; what signed ordinance, resolution and minutes record the result?
- What are comment deadlines, next hearings, appeal windows, permit expirations, extensions and resubmission rules?
IC-05 · Withdrawal, moratorium and vested rights
- What signed withdrawal, delivery timestamp, acceptance and closed-case record establish withdrawal?
- Which applications, agreements or permits survive a withdrawal; can the applicant refile?
- What enacted moratorium text, effective and expiration dates, exceptions and transition rules apply?
- What actual vesting instrument, ordinance or agreement establishes claimed grandfathering, and when does it expire?
IC-06 · Study register and independent review
- Which completed, draft, preliminary and pending studies exist, and which studies were waived or not required?
- For every study: who commissioned, performed, paid for and reviewed it; what firm, author, qualifications, date, scope, contract and fee?
- What assumptions, models, appendices, underlying data, revisions and peer-review responses support conclusions?
- Do studies cover full buildout, cumulative nearby projects, alternatives and worst-case conditions rather than one phase?
IC-07 · Site alternatives and cumulative impacts
- What alternative sites, sizes, cooling designs and no-build scenarios were compared?
- Why was this site selected; what land, power, water and incentive assumptions drove that decision?
- What other approved or proposed industrial loads affect the same water, grid, roads and communities?
- What capacity thresholds or combined impacts could invalidate the conclusions?
IC-08 · Water supply, rights and cooling
- What sources, rights, well permits, decrees, supplier agreements and legally available yield support the project?
- What are daily, annual and peak withdrawals and consumptive use, by phase and full buildout, including drought and hottest-day scenarios?
- What cooling technology, cycles, PUE/WUE assumptions, treatment chemicals and emergency alternatives are proposed?
- Who funds water acquisitions and system upgrades; which restrictions protect existing users during scarcity?
IC-09 · Wastewater and sewer
- What discharge volume, temperature, chemicals, salinity and pretreatment are expected?
- What collection, treatment, discharge-permit and receiving-water capacity is reserved?
- Which intergovernmental or provider agreements allocate service, costs and liability?
- What monitoring, reuse, spill response and shutdown conditions are enforceable?
IC-10 · Power, interconnection and grid costs
- What utility, maximum load, ramp schedule, interconnection queue/study IDs and service commitment apply?
- What generation, transmission, substation and distribution upgrades are needed, with completion dependencies?
- Who pays capital and continuing costs; what deposits, tariffs, reimbursements and stranded-asset guarantees protect other ratepayers?
- What curtailment, demand response, reliability and backup scenarios were evaluated?
IC-11 · Equipment, servers and AI chips
- Which server OEMs, chip suppliers, rack/integrator firms, tenants and equipment models are documented?
- What procurement contracts, equipment schedules, permit drawings or agency-held bids identify them?
- What transformers, switchgear, generators, UPS, battery chemistry and cooling equipment are specified?
- Which specifications remain unselected or confidential, and what lawful public version is available?
IC-12 · Construction, steel and concrete
- Who are the general contractor, engineers, architects and subcontractors, and what scope does each hold?
- Which steel fabricators, concrete suppliers and hauling/disposal vendors are documented?
- What material quantities, construction phases, work hours, staging areas and delivery routes are planned?
- Who funds inspections, road repairs, dust/noise controls, worker safety oversight and restoration?
IC-13 · Fiber, telecom and rights of way
- What carriers, fiber owners, routes, redundancy and connection agreements support the site?
- Which easements, conduit, crossing/boring and highway/right-of-way permits are required?
- Who owns and maintains the infrastructure, and who pays initial and ongoing costs?
- What construction disruptions, security constraints and public disclosure limits apply?
IC-14 · Noise, vibration and lighting
- What baseline and modeled continuous, tonal, low-frequency and cumulative noise reaches homes and schools?
- Do studies include nighttime operation, generator tests, simultaneous equipment and full buildout?
- What lighting/photometric, glare, vibration and screening analyses exist?
- What enforceable limits, measurement locations, independent monitoring and corrective deadlines apply?
IC-15 · Air, generators and climate
- What generator counts, ratings, fuel, annual testing and emergency run hours are proposed?
- Which air permits, emissions inventories and dispersion/health assessments cover normal and backup operation?
- How are diesel particulate matter, NOx, ozone precursors and nearby cumulative sources evaluated?
- What energy/emissions assumptions and enforceable commitments cover the full campus rather than marketing claims?
IC-16 · Fire, batteries, fuel and emergencies
- What battery chemistry, fuel storage, hazardous materials and worst-case fire/spill scenarios are planned?
- Which fire code, emergency-access, water-flow and response-capacity reviews were performed and by whom?
- What public emergency plans, drills, mutual-aid agreements and responder training will exist?
- Who pays additional staffing/equipment, containment, cleanup and insurance; what financial assurance is binding?
IC-17 · Soils, contamination and geotechnical
- What Phase I/II environmental site assessments and historic-use records identify contamination or other liabilities?
- What geotechnical, groundwater, subsidence, foundation and soil-management studies exist?
- What sampling methods, lab results, cleanup plans and regulator closure decisions support safe reuse?
- Who pays remediation and bears liability for newly discovered contamination?
IC-18 · Stormwater, floodplain and drainage
- What hydrology, floodplain, drainage, erosion-control and stormwater permit analyses cover buildout?
- How do impervious area, detention, extreme rainfall and downstream impacts change?
- Who owns, funds and maintains detention and drainage facilities, including failure response?
- What inspection, monitoring, bond and maintenance conditions protect neighbors?
IC-19 · Wetlands, wildlife and ecological impacts
- What wetlands, waters, habitat, threatened-species and seasonal field surveys exist?
- Which state/federal permits or consultations are triggered, and what written applicability decisions support exemptions?
- What loss, mitigation, restoration and cumulative ecological impacts were evaluated?
- Who funds and verifies mitigation over its required lifetime?
IC-20 · Traffic, roads and community health
- What construction-haul and operating traffic studies address safety, crossings, emergency access and cumulative growth?
- What effects on residences, schools, vulnerable populations, air, heat, noise and property access were evaluated?
- What community consultation, accessible/translated notices and neighboring-government responses were recorded?
- Which road improvements, buffers, complaint processes and community protections are binding?
IC-21 · Jobs and economic claims
- How many direct permanent FTE jobs, contractors, temporary construction workers and job-years are projected by phase?
- What wages, benefits, local hiring assumptions and source/method support those numbers?
- Are indirect and induced jobs separated from on-site employment; are figures campus-specific and net of displaced jobs?
- What enforceable employment targets, reporting, independent verification and clawbacks apply?
IC-22 · Public money, financing and contracts
- What capital, operating and lifetime public costs are attributed to the project, including utilities, roads and emergency services?
- What incentives, abatements, fee credits, grants, loans, bonds, reimbursements, public land or guarantees were negotiated?
- Who receives payments and benefits; what contracts, invoices, study fees and cost-sharing terms document the money trail?
- What net fiscal analysis, risk allocation, security, reimbursement triggers and clawbacks protect residents?
IC-23 · Transparency, conflicts and accountability
- What NDAs, signing authority, exemption determinations and public/redacted versions exist?
- What government-held meeting logs, lobbying, campaign disclosures, gifts, conflicts, recusals and executive-session records are relevant?
- Who has authority to approve changes, inspect, enforce conditions and respond to complaints?
- What record retention, periodic public reporting and independent audit requirements apply?
IC-24 · Operating monitoring and closure
- What meters, sampling, continuous noise/air monitoring and public performance reports are required?
- What inspections, violation thresholds, corrective deadlines, penalties and suspension/shutdown powers are enforceable?
- What ownership-change, expansion, cooling/equipment-change and permit-renewal triggers require new review?
- What decommissioning, abandoned-site, cleanup and restoration plans, bonds and financial security cover closure?
Study register: who performed it, who paid, and who checked it?
Obtain the study title, project/parcel, author and firm, qualifications, commissioning party, payer, contract and fee, draft/final date, scope and study phase, assumptions and underlying data, full-buildout/cumulative scenarios, reviewer, review comments, revisions, acceptance date, conditions and remaining gaps. Track pending studies and written waiver/applicability decisions. Do not assume all listed studies are required by law at every site.
Time frames that must be documented
Pre-application → filing → completeness → referrals and studies → public notice and comments → hearing and vote → signed action and effective date → appeal period → utility and building permits → construction phases → inspections → occupancy/operation → monitoring/renewal → closure. Record exact dates, authority and dependencies, plus expirations, extensions and changes. An agenda entry alone does not establish passage.
Project-specific gaps
- Silo: Reported withdrawn; obtain the applicant’s written withdrawal, City acceptance and surviving applications/rights. Official Weld land account R8052899 identifies parcel 147134000073; the identified parcel is in Weld County. Keep county and municipal approval authority separate.
- Cielo Hudson: Cielo Digital Infrastructure is separate from Global AI. The 750 MW / 500-acre proposal is reported; exact parcel, jurisdiction, application, site-specific studies, vendors and jobs remain unresolved. Hudson’s townwide water plan is not a Cielo study.
- Fort Lupton / 1.21: Parcel 147122200006 / R8967608, recorded transfer trail and water affidavits provide leads. Obtain full annexation case, study authors, utility commitments, jobs, vendors, costs and binding conditions. A recorded transfer does not establish project approval.
- Global AI: Maintain a separate case and distinguish approved footprint, phases, projected maximum load and actual operating capacity.
Records-request fee rule: No fees are authorized. Obtain an itemized estimate and express written DCAP approval before chargeable work. Request existing records and staged indexes first; do not ask custodians to create studies or presume they hold private procurement records.
Map/database quality: Separate published water figures from modeled estimates. Label utility service-territory assumptions as inferred. Do not present a precise Cielo map point without a verified parcel. Keep reported withdrawal distinct from official closure.
VERIFIED TRANSMISSION STATUS · OCTOBER 12, 2026
Questions published. Request status stays separate.
- Brighton: Silo written withdrawal, study authors, jobs and public costs supplement sent to the City Clerk at 10:02 p.m. Mountain time; verified in Sent. R000429-092326 cross-referenced. No new acknowledgement verified.
- Fort Lupton: 1.21 annexation, studies, vendors, jobs and costs email sent to the City Clerk at 10:07 p.m.; verified in Sent. Official-form/intake acceptance remains pending.
- Weld Recorder: Eight deed/recorded instruments requested at 8:48 p.m.; verified in Sent. Full instruments and acknowledgement not yet obtained.
- Lochbuie: Identified Consor invoice and supplemental scope prepared; send attempt unverified. Do not count as submitted.
- Hudson/Cielo and Weld Cielo/Global AI: Drafts prepared. Hudson official form completed. These new requests remain unsent.
No fees are authorized. Itemized written estimate and express written DCAP approval are required before chargeable work. The email workspace’s credential-protection error blocked the remaining sends; recovery was attempted. Publishing these questions does not submit the drafts.
Read all 96 critical questions. A study inventory records what must be obtained; it does not establish that a study exists, was reviewed or cleared a project.