MW demand, utilities, substations, generation and who pays
| Item | Status | What we know / need | Next action |
|---|---|---|---|
| Brighton regulatory work | ACTIVE | City identifies electrical power as a moratorium policy issue | Request utility/interconnection studies and cost allocation |
| Global AI / Weld | ACTIVE | County rules require electricity will-serve documentation | Obtain will-serve letter and utility records |
| Federal policy | CONFIRMED | Ratepayer pledge says developers should cover added generation and grid upgrades | Compare Colorado projects to pledge and tariff structures |