DATA CENTER ACCOUNTABILITY PROJECT
LIVE TRACKER

CORA / Public Records Queue

Requests to send, submitted requests and missing records

ItemStatusWhat we know / needNext action
Brighton — Project Silo withdrawalSEND / VERIFYWritten withdrawal scope, acceptance and complete recordSubmit/reconcile portal request and confirmation
Brighton — Oct 6 + Oct 20 moratoriumSEND / VERIFYFinal ordinance, motions, roll call, effective dateSubmit/reconcile portal request
Brighton — infrastructure / utilitiesSENDPower, water, wastewater, traffic, acoustic, lighting, generator and battery recordsSubmit scoped CORA / utility requests
Weld — Global AISEND / EXPANDPermit record exists; need utility, water, noise, future-phase and enforcement recordsRequest full case plus enforcement history
Fort LuptonSUBMITTEDRequest form previously submittedTrack response, fee estimate and production
Adams CountyREADY / TRACKRegional consultation, infrastructure, NDAs, contracts and paymentsSubmit/verify receipt and deadline